Bangalore Electricity Supply Company Limited Vs. Hirehalli Solar Power Project Llp & Others

  Supreme Court Of India Civil Appeal /7595/2021
Link copied!

Case Background

The short issue arising from these appeals is whether the extension of the Scheduled Commissioning Date was occasioned under the force majeure clause of the Power Purchase Agreement and consequently ...